Retaining Wall - the wall is officially done. That doesnt mean it is actually finished, it just means the deal is over and the wall builders have left. I am glad it's done.
July 1 Trash haul off
July 2 Backfill has been done
July 6 Dirt is all spread out, holes filled and remainder hauled off
Steps nearest pool did not get completed
Acid wash did not happen
Big Steps will stay like they are
I will have to do these things myself as there was some communication problem and it didn't get included in the deal.
Pool Tile - Pool tile has been installed as of July 7. We are picking out some accent tile to use on the steps at the time of surfacing.
Pool Plumbing - Pool plumbing should start July 12
Pool Surfacing - Should start by end of week of July 12. At this point, we are going with Tahoe Blue
Pavillion - Now we are talking about having a wooden post pavilion created that has a fireplace.
Landscaping - Sodding is scheduled for week of July 12.
TV - The TV people have been out and found an electrical problem, that they caused. We had an electrician repair the problem and who knows when the satellite will now be repaired.